Mathews Inc.
Bear camp construction has begun
Bears
Contributors to this thread:
Craig 22-Feb-15
Topgun 30-06 22-Feb-15
CurveBow 24-Feb-15
CurveBow 24-Feb-15
Bou'bound 24-Feb-15
Paul@thefort 24-Feb-15
elmer@laptop 25-Feb-15
Chris S 26-Feb-15
Craig 27-Feb-15
elmer@laptop 27-Feb-15
Bou'bound 28-Feb-15
Craig 01-Mar-15
Craig 01-Mar-15
Craig 01-Mar-15
jmail20 02-Mar-15
Craig 04-Mar-15
Alexis Desjardins 05-Mar-15
Craig 05-Mar-15
Craig 13-Mar-15
Charlie Rehor 13-Mar-15
Craig 23-Mar-15
Craig 28-Mar-15
Craig 28-Mar-15
Craig 28-Mar-15
From: Craig
22-Feb-15

Craig's embedded Photo
Craig's embedded Photo
We have the floor built for the bear camp cabin.

From: Topgun 30-06
22-Feb-15

Topgun 30-06's embedded Photo
Topgun 30-06's embedded Photo
Try this!

From: CurveBow
24-Feb-15
Good luck with that and congrats on getting it started!

>>>>-------->

From: CurveBow
24-Feb-15
Good luck with that and congrats on getting it started!

>>>>-------->

From: Bou'bound
24-Feb-15
thanks for sharing

From: Paul@thefort
24-Feb-15
should go up quickly now. Just make sure once the snow melts and the ground thaws, the floor will remain level. can not tell if the floor is on sunken pylons.

Cool project.

From: elmer@laptop
25-Feb-15
Cool, where are you building?

From: Chris S
26-Feb-15
Cool, I love watching builds. Inspires my daydreams about someday building my own. Enjoy post lots of pics along the way!!

From: Craig
27-Feb-15
Thanks topgun for fixing my pic. The floor is on cement blocks with 4x4's that fit inside. Its on a gravel ridge so it should not move to much.Im building it in Ste rose Manitoba back in the bush. Should be ready for the spring bear hunters. Building the walls this weekend and maybe the roof.

From: elmer@laptop
27-Feb-15
Awesome!

From: Bou'bound
28-Feb-15
when do you expect the plumbimng phase to commence

From: Craig
01-Mar-15

Craig's embedded Photo
Craig's embedded Photo
Got the walls up and rafters on ready for strapping and tin than i will do the plumbing and wiring.

From: Craig
01-Mar-15

Craig's embedded Photo
Craig's embedded Photo

From: Craig
01-Mar-15

Craig's embedded Photo
Craig's embedded Photo

From: jmail20
02-Mar-15
Hey Craig, looks like you guys are moving right along. If you lived down here I'd hire you!! Can always use a good framing crew. See you in a couple months.

From: Craig
04-Mar-15
Sounds good looking forward to it joe.

05-Mar-15
Looking good there nephew that didn't take long to get that part up.

From: Craig
05-Mar-15
Thanks uncle hopefully have it ready to go in april.

From: Craig
13-Mar-15
Hopefully have the tin on this weekend and some wiring done.

13-Mar-15
Yes, Craig is a sponsor!

From: Craig
23-Mar-15
Tin is on inside walls built and some wiring done.

From: Craig
28-Mar-15

Craig's embedded Photo
Craig's embedded Photo
Here are some pics i took today. Got some snow during the week got the roof tinned just in time.

From: Craig
28-Mar-15

Craig's embedded Photo
Craig's embedded Photo
I made the brick mold for the windows i bought with 2x4s

From: Craig
28-Mar-15

Craig's embedded Photo
Craig's embedded Photo

  • Sitka Gear